DESTRUCTION OF FIVE PRODUCTION WELLS, APTOS, CAPITOLA, & SOQUEL,

The work includes destroying five (5) production wells to block pathways for potential contamination of aquifer units through voids between the casing and annular material, voids between the borehole and annular material, and gravel pack across multiple aquifers. 

Contractor shall acquire well destruction permits from the County of Santa Cruz.  Prior to destroying each well the well shall be cleaned as needed, and the casings perforated.  The destruction of all wells shall comply with state and county provisions.