PWS Conveyance Project

Latest Update: February 16, 2024

All construction dates are subject to change due to weather or unforeseen circumstances. Please note that some repaved roadways within the project area currently have only temporary striping. Final roadway striping will be done at a later date. Thank you for your patience.

Project Contractor: Garney Construction


City of Santa Cruz  

  • Laurel Street Bridge: (Work hours are Monday through Friday, 7:00am–4:00pm)
    • No work today (2/16) and Monday (2/19) for union holiday. 
    • Architectural cover work is in progress at the Laurel Street Bridge and will continue through May.
  • Laurel Street: (Work hours are Monday through Friday, 7:00am–4:00pm)
    • No work on Monday (2/19) for union holiday. 
    • Isolated work, concrete, and temporary paying are underway at Felix Street, between Walti Street and Blackburn Street. This work activity is anticipated to be completed on 2/23. Final paving begin in March.
  • All streets along the pipeline alignment: 
    • Appurtenance and paving work underway
    • Final paving: March 2024
    • Final micro surfacing over paving: Late April to early May 2024
    • Final striping: Mid to late May 2024


Soquel/City of Capitola/Aptos/County of Santa Cruz

  • Soquel Avenue: (Work hours are Monday through Friday, 9:00am–4:30pm)
    • From 17th Avenue to Chanticleer Avenue, leak repair, pressure testing, and temporary paving continue. 
  • Rosedale Avenue and Kennedy Drive (Work hours are Monday through Friday, 8:00am-5:00pm on Kennedy Drive and 8:30am-4:30pm on Rosedale Avenue)
    • No work on Monday (2/19) for union holiday. 
    • Repair work is underway and will continue for approximately one week. Following the repair, crews will begin pressure testing and related work. 
  • All streets along the pipeline alignment: 
    • Appurtenance and paving work underway
    • Final paving: March 2024
    • Final microsurfacing over paving: Late April to early May 2024
    • Final striping: Mid to late May 2024

Motorists, cyclists, and pedestrians will encounter traffic controls. Be aware of signage, flaggers, detours, and changes to lane configurations.  

  • Follow all traffic controls and designated detours, and do NOT pass-through Road Closed signage; consider using alternate routes.  
  • Use extra caution when on any roads in the vicinity of the construction activity and watch for turn restrictions, equipment, and work crews.
  • Access to some side streets may be temporarily impacted during construction. 
  • There may be construction equipment or vehicles parked on side streets—please be aware of temporary “No Parking” signs. 
  • Please watch for work crews and equipment and be prepared for traffic delays—allow additional time to get to your destination. 
  • Some roadways may be temporarily uneven or rough. 
  • If there are questions about this work, please call (831) 475-8501 ext. 148.

Project Summary:

Contractors for Soquel Creek Water District are installing about eight miles of pipeline under various streets between Santa Cruz and Aptos. These pipelines will carry water to and from the Santa Cruz Wastewater Treatment Facility to the Chanticleer Water Purification Center (to be built) in the Live Oak area. Then purified water from the Water Purification Center will be conveyed to three Seawater Intrusion Prevention (SWIP) wells, where it will recharge the groundwater basin. 

Construction will not be taking place on all streets along the pipeline route simultaneously. It will be a moving work zone, progressing up to several hundred feet per day. Work within a particular area could last for one-to-two weeks or more as construction crews move along the pipeline route. 

In most cases, the work will consist of excavating through the asphalt street surface, preparing the area for the pipelines, delivering and laying the pipes and associated equipment, then backfilling and temporarily patching of the street (to be resurfaced later). This work will require trucks, backhoes, excavators, and other equipment, with traffic control work crews on-site. In some areas, the pipeline will go across bridges where it will be affixed to the bridge structure. The work will require lane closures and short detours and in some cases may require temporary complete closure of a segment of the street.

Project Map

Map of all the components of the Pure Water Soquel Project. As pipeline construction continues along the route, this map will show that progress.